Sunday, 29 April 2012

End of Week 12

Progress is at a bit of a 'stutter' at the minute.

Plastering was finished Wednesday. All looking good just dying out.

Power was jointed Thursday but I don't get my meter till this coming Thur, then it's bye bye to the old genny. Plumber didn't get there Friday, but should start tomorrow. Sparks is going back in late week to coincide with getting the meter and mains electric.

As plans stand now i'll probably be fitting the kitchen late week, minus end panels and plinths, which will go on after the finished floor. Still, there will be plenty of other second fix joinery to go at with the skirting's, arc's and cupboard shelves.

Have chosen the bathroom tiles and a picture is below. Using a ceramic 'stone effect' tile on the floor and up the walls, with the travertine mosaic as a border and for the shower floor. Need to get the shower enclosure ordered and on site before any bathroom tiling. As it's an offset quadrant shape, the tiles around the shower will have to be cut to the metal profile of the enclosure. The joint between the ceramics and mosaics will then be underneath the enclosure. Obviously grouted and done neatly, so if anyone ever wanted it as a wet room suitable for a wheelchair then all they would have to do is unscrew the enclosure and replace with a curtain.

No comments:

Post a Comment