End of Week 17


White ceilings this week. Vin's got a couple of coats on today and will start the walls tomorrow. Just getting the emulsion done then off till I'm ready for the glossing.

Seen plumber Friday, says he will be able to come and finish off after next weekend (i.e. week 19) Gas meter due for this Thursday. The fitter who came a few weeks ago had a dodgy meter apparently.

Knocked all the gravel about today. Levelled off around the back and side, got rid of the remaining sand, covered in landscape fabric then gravelled over. 4 Tonne in all but needed one more. I'll have to pick one up loose. I was planning to gravel in the planter too but may bark now.

Spoke to someone about an air test late last week. Apparently behind kitchen units and bath panel are the most common points of failure/leakage. I'll keep this in mind when i'm finishing off the kitchen, i've already gone mad with silicone and boards behind the bath.

Shower has come together. How ever long you think it takes to assemble a shower enclosure, double it! Very fiddly. But went into the space perfectly. All level and plumb. Just needs the mosaics finishing up to the enclosure and sealing then it's done. These had to be left out as they are slightly proud of the rest of the tiles (ceramic against natural stone). Anyway, happy with my carefully planned, wetroom adaptable bathroom.

So this week shall book air test in for when 2nd fix is finished, may finish off fence and gates and hopefully get a chance to seed the lawn. Debating whether to do floor before or after plumbers been back...
 